Internal Audit

 

 

 

Progress Report 2022-23

 

 

 

West Devon Borough

 

Audit Committee

 

 

 

22 November 2022

 

 

 

 

 

 

 

 

Tony Rose
 Head of Audit Partnership


Contents

Page

Introduction

1

Opinion Statement

2

Executive Summary of Audit Results

2

Value Added

3

Audit Coverage & Progress Against Plan

3

 

 

 

 

 

 Appendices

 

1 – Summary of Audit Results

2 – Progression of audit plans

4

10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Introduction

The Audit Committee, under its Terms of Reference contained in West Devon’s Constitution, is required to consider the Chief Internal Auditor’s annual report, to review and approve the Internal Audit programme, and to monitor the progress and performance of Internal Audit.

 

The Accounts and Audit (Amendment) (England) Regulations 2015 introduced the requirement that all Authorities carry out an annual review of the effectiveness of their internal audit system and incorporate the results of that review into their Annual Governance Statement (AGS), published with the annual Statement of Accounts.

                                                                                

The Internal Audit plan for 2022-23 was presented and approved by the Audit Committee in March 2022. The following report and appendices set out the background to audit service provision and provides a position statement on the overall adequacy and effectiveness of the Authority’s internal control environment.

 

The Public Sector Internal Audit Standards require the Head of Internal Audit to provide an annual report providing an opinion that can be used by the organisation to inform its governance statement. This report contributes to that annual opinion.

 

Expectations of the Audit Committee from this progress report

Audit Committee members are requested to consider:

·         the assurance statement within this report.

·         the basis of our opinion and the completion of audit work against the plan.

·         the revised audit plan provided.

·         audit coverage and findings provided.

·         the overall performance and customer satisfaction on audit delivery.

 

In review of the above the Governance Committee are required to consider the assurance provided alongside that of the Executive, Corporate Risk Management and external assurance including that of the External Auditor as part of the Governance Framework and satisfy themselves from this assurance that the internal control framework continues to be maintained.

 

Tony Rose

Head of Devon Audit Partnership



Overall, based on work performed during 2022/23 and our experience from the current year progress and previous years’ audit, the Head of Internal Audit’s Opinion is of “Reasonable Assurance” on the adequacy and effectiveness of the Authority’s internal control framework.Opinion Statement

This opinion statement will support Members in their consideration for signing the Annual Governance Statement.

Internal Audit assesses whether key, and other, controls are operating satisfactorily within audit reviews. An opinion on the adequacy of controls is provided to management as part of each audit report. 

All final audit reports include an action plan which identifies responsible officers, and target dates, to address control issues identified. Implementation of action plans is the responsibility of management but may be reviewed during subsequent audits or as part of a follow-up process.

Directors and Senior Management are provided with details of Internal Audit’s opinion for each audit review to assist them with compilation of their individual annual governance assurance statements at year end.

Substantial Assurance

A sound system of governance, risk management and control exist across the organisation, with internal controls operating effectively and being consistently applied to support the achievement of strategic and operational objectives.

Reasonable Assurance

There are generally sound systems of governance, risk management and control in place across the organisation. Some issues, non-compliance or scope for improvement were identified which may put at risk the achievement of some of the strategic and operational objectives.

Limited Assurance

Significant gaps, weaknesses or non-compliance were identified across the organisation. Improvement is required to the system of governance, risk management and control to effectively manage risks and ensure that strategic and operational objectives can be achieved.

No Assurance

Immediate action is required to address fundamental control gaps, weaknesses or issues of non-compliance identified across the organisation. The system of governance, risk management and control is inadequate to effectively manage risks to the achievement of strategic and operational objectives.

 

 

Executive Summary of Audit Results

Key Financial Systems

We provide a Substantial Assurance on Treasury Management, and a Reasonable Assurance on management of Payroll during 2021/22 using the TeamSpirit software. We have also started this year’s Payroll audit on the new system and will provide a report in a few weeks. We also provide a Substantial Assurance related to post payment assurance of Covid 19 - Business Grants.    

Risk Based Audits

We provide reports on some priority areas, in particular one related to Climate Change (Reasonable). We also provide a Substantial Assurance on Contract Management of the Leisure Centres.

Appendix 1 of this report provides more detail on the audits delivered since the last Committee meeting with the overall assurance opinion and recommendations. Where a “substantial assurance” or “reasonable assurance” of audit opinion has been provided we can confirm that, overall, sound controls are in place to mitigate exposure to risks identified; where an opinion of “limited assurance” has been provided then issues were identified during the audit process that required attention. We have provided a summary of key issues reported that are being addressed by management. We are content that management are appropriately addressing these issues.

Counter Fraud Work

Recent assessments state that there is an epidemic of fraud cases. Fraud now account for 40% of all crimes; it is anticipated that this will further increase by 25% in the coming years (see Fraud and the Justice System). The government has responded with formation of the Public Sector Fraud Authority. Given this landscape, it is important for councils to have effective measures to reduce the risk and impact of fraud.

We plan to undertake Fraud Risk Assessment in most of the District Councils we support in the next few months including South Hams and West Devon. We intend to present the results to Audit Committee.

We are not aware of any reported fraud issues in the year to date. Management is aware that they can refer any suspected issues to our specialist counter fraud team.

Recommendation Tracking

We understand that management continues to review audit recommendations made by internal audit since April 2020 to confirm that they are implemented or work taking place to implement them. In undertaking audits, we continue to find audit recommendations (some High Priority) from previous audits that have not been progressed. 

Value Added

It is important that the internal audit service seeks to "add value" whenever it can. We consider internal audit activity has added value to the organisation and its stakeholders by:

·      Providing objective and relevant assurance.

·      Contributing to the effectiveness and efficiency of the governance, risk management and internal control processes.

·      Adjusting the audit plan when needed to provide real time assurance.

·      Comparing and contrasting controls across the different Devon Councils that we support.

Audit Coverage and Performance Against Plan

We have almost completed all the audits from the 2021-22 audit plan. Appendix 2 provides detail on these audits, as well as detail on the 2022-23 audit plan.

Progress to deliver the 2022-23 plan has been impacted by continued diversion of one of the two core auditors to administer the Covid Business Grants for the council. We anticipate this work may shortly complete. In addition, the LAG / LEAF work is expected to continue into 2023. We estimate this means we are short of more than 65 days from this financial year. We are subsequently using additional DAP resource to support audit plan delivery. Part of this resource is undertaking a comprehensive Cyber Security audit provided by One West (a DAP strategic partner), and other audits supported by the DAP team such as a risk management review.

Chart: Delivery of the 2022-23 audit plan

This chart states that there are two Final Report, Two draft reports, four audits in fieldwork. The rest of the audits are in planning or not yet started.

Customer Satisfaction

We have had no recent satisfaction returns. We will be placing emphasis on obtaining feedback for current audits.   

 


Appendix 1 – Summary of audit reports and findings for 2021-22

 

Audit / Assurance Opinion

Summary, risk exposure and management actions

Covid 19 - Business Grants Post-Scheme Assurance

 

Substantial Assurance

The process for distributing grants has been hugely successful: between March 2020 and March 2022, across all schemes, SHDC paid approximately 16,600 grants with a total value of almost £86m, whilst WDBC paid over 6,000 grants with a total value of £33.5m.

The small number of grants subsequently identified by post-payment checks as being non-compliant or paid in error demonstrates the success of the comprehensive range of manual and automated pre-payment checks in place. At £142k, they made up just 0.1% of the total value of grants paid.

We confirm that all these cases of suspected fraud or error have been investigated and recovery sought as appropriate. Where possible, overpayments were recovered from future grants due to the applicant, otherwise a debtor's invoice was raised. At the time of our review the majority of the £142k had been recovered. There is £52.2k outstanding (0.04% of the total grant payments), one third of which are being repaid in instalments by the recipients.

The Councils' robust approach to accepting and processing grant applications, has also minimised the occurrence of fraud. At the time of writing, there were seventeen cases of suspected fraud, with grants having been paid in only three instances (total value £25k), and all were being investigated. Post-payment checks continue to be made by officers and so may highlight additional cases.

We did not agree any High recommendations.

Treasury Management

 

Substantial Assurance

The Councils are adhering to legislative and regulatory requirements and have appropriate and effective controls in place over treasury management operations. The Councils continue to follow a cautious investment strategy, the investment priorities being the security of capital, the liquidity of investments and yield.

Interest rates and actual returns were low (0.07% for both Councils in 2021/22) reflecting the low interest environment: rates will inevitably be much greater for 2022/23. Appropriate expert advice was obtained on investments, and there was a good process to record and administer individual investments. Investments are made only in institutions on their approved lending list, which is regularly reviewed based on credit agency and market information.

Use is also made of the Public Works Load Board; at the end of 2021/22 this constituted 17 loans (£14.38m) for South Hams, and 30 loans (£27.73m) for West Devon, most are to fund leisure investment loans to Fusion, and to fund projects. We understand no loans are likely from the PWLB this year.

There is appropriate segregation of duties related to system administration and raising and approval of CHAPS payments and investment made through the Sungard portal.

We did not agree any High recommendations.

Contract Management – Leisure

 

Substantial Assurance

Based on the systems and processes provided, we confirm the Councils are effectively undertaking their duties with regard to managing the leisure facilities through the DBOM Contract. In the last couple of years, this has included effective financial and risk assessment of the viability of the contractor to ensure leisure services could continue, at best value for money.

Attendance and membership levels have improved and are at near pre-pandemic levels improving future financial viability. Centre participation across all 6 leisure centres in South Hams and West Devon has increased since re-opening from c19,500 to c62,000 in January 2022. When compared to January 2020 of c64,000 this represents a 97% usage rate close to pre-Covid levels. The councils are effectively monitoring contractor performance to ensure it continues to deliver as per the contract. There is also active review of the financial viability of the contractor.

We make some recommendations and restate some that have not been implemented from our last audit in 2018/19 (including the two High Recommendations stated below). 

The agreed High recommendations related to:

1.    Business Continuity - Identifying options if the current operator cannot continue to deliver the service (although an options appraisal was undertaken in September 2020).

2.    Obtain a copy of all building warranties and contracts for work completed by Fusion.

Climate Change

 

Reasonable Assurance

The Councils have made progress to reduce their carbon emissions. For example:

·         Significant reductions in commuting and business mileage due to continued remote working practices.

·         Some of the light vehicle fleet have been replaced with electric equivalents; work is underway to continue this rollout.

·         Funding allocated for solar panel installation across the leisure centres (£500k for the four SHDC centres and £300k for the two WDBC centres).

·         £0.25m across SHWD for decarbonisation planning at the six Leisure Centres from Public Sector Low Carbon Skills Fund.

Projects to support the net zero target across the wider community are also underway:

·         Installation of electric vehicle charging points at several Council-owned public car parks; and

·         Continued allocation of £900k (SHDC) and £600k (WDBC) in Green Homes Grants to allow eligible households to deliver energy saving measures.

However, the councils do not have an agreed baseline of carbon emissions over successive years meaning it is not possible to confirm emissions are reducing. There has also been no detailed scoping of the many projects in the Action Plans so that understanding is limited of the funding required to deliver them.

We did not agree any High Recommendations.

We made several Medium recommendations including: to ensure a clear baseline of emissions; to develop the Actions Plans to reach Net Zero; to create an Adaptation Plan; and maintain a risk and opportunities register.

Payroll (21/22 plan)

 

Reasonable Assurance

The 2021/22 arrangements for delivery of the payroll function have been operated as effectively as possible, within the limitations of the TeamSpirit software. Despite the continued need to undertake some manual calculations, it has not led to errors in the payroll as there were appropriate checks and controls for data input and manual calculations. Payments to staff appear to have been made accurately, with very few overpayments and advances of pay required due to errors.

We have repeated two minor recommendations from last year, as we were unable to confirm they had been implemented due to the unavailability of Payroll staff who were involved in the testing and implementation of the new payroll system.

We maintained some oversight of this latter piece of work, seeking assurance that shortcomings within the TeamSpirit system were not being duplicated in the new payroll system (i-Trent) that is now in place.

We did not agree any High Recommendations.

 

 

 

 


 

Appendix 2 – Progress on the audit plan

2021/22 Audits

 

Audit

Business Area

Assurance Opinion

Comments

Payroll

KFS

Reasonable

See summary in Appendix A

Change Control – Business Processes

 

Tbc

Report being drafted

Salcombe Harbour

Place & Enterprise

Tbc

Report being drafted

 

2022/23 Audits

Audit

Business Area

Assurance Opinion

 

Comments

Final Report issued / Work Completed

Development Management - Section 106 Arrangements

Customer Service & Delivery

Reasonable Assurance

 

Summary provided in previous meeting.

Climate Change

Governance & Assurance

Reasonable Assurance

See summary in Appendix A

Covid19 - Business Grants Post-Scheme Assurance 2022/23

Place & Enterprise

Substantial Assurance

See summary in Appendix A

Treasury Management

KFS

Substantial Assurance

See summary in Appendix A

Contract Management - Leisure

Governance & Assurance

Substantial Assurance

See summary in Appendix A

 

 


 

Audit

Business Area

Comments

 

Draft Report

Corporate Strategy and Performance Management

 

Governance & Assurance

Draft issued 16 September 2022. Work now being undertaken with management to finalise the report.

Building Maintenance - Works Scheduling Follow Up

                                   

Customer Service & Delivery

Draft issued 13 June. Work being prioritised to obtain management agreement to the report. 

Health and Wellbeing

Customer Service & Delivery

Draft Report issued 19 October 2022

Procurement – compliance with financial procedures and tender limits

Governance & Assurance

Draft Report issued 15 November 22

Fieldwork

Risk Management

Governance & Assurance

To be undertaken in November 2022.

Corporate Information Management

Governance & Assurance

To be undertaken in November 2022

Capital Expenditure

Place & Enterprise

 

ICT Cyber Security

Customer Service & Delivery

 

Payroll

KFS

Work started 4 Nov 22

Grants LAG LEAF 2022/23

 

Other items

Ongoing work to validate this grant.

 

 

Contingency, Advice & Emerging Risks

 

Other items

Ongoing

National Fraud Initiative

Other items

Ongoing

Exemptions from Financial Regulations

 

Other items

Ongoing

 

Planning / Not Yet Started

Main Accounting System

 

KFS

Indicative start Q4

Creditor (Payments)

 

KFS

Indicative start Q3

Debtors (Income Collection)

 

KFS

Indicative start Q3

Business Rates

KFS

Indicative start Q3

Council Tax

 

KFS

Indicative start Q3

Housing Benefits

 

KFS

Indicative start Q3

Regeneration and Investment Strategy

 

Place & Enterprise

Indicative start Q4

Locality Officers

 

Customer Service & Delivery

Indicative start Q3

 

Partnership Funding Arrangements

 

Customer Service & Delivery

Indicative start Q3

 

Project Management

 

Governance & Assurance

Indicative start Q4

Future IT Project

Governance & Assurance

Indicative start Q2

VAT Arrangements

Governance & Assurance

Indicative start Q3

Business Continuity / ICT Business Continuity

Governance & Assurance

Indicative start Q3

Devon Audit Partnership

The Devon Audit Partnership has been formed under a joint committee arrangement comprising of Plymouth, Torbay, Devon, North Devon, Mid Devon and Torridge councils.  We aim to be recognised as a high-quality internal audit service in the public sector.  We work with our partners by providing a professional internal audit service that will assist them in meeting their challenges, managing their risks and achieving their goals.  In carrying out our work we are required to comply with the Public Sector Internal Audit Standards along with other best practice and professional standards.

The Partnership is committed to providing high quality, professional customer services to all; if you have any comments or suggestions on our service, processes or standards, the Head of Partnership would be pleased to receive them at robert.hutchins@devonaudit.gov.uk .